Tongue Twister: Commander Closes Construction Site for COVID and Contractor Can’t Recover Contract Costs
Best Practices Construction Law
JUNE 21, 2022
62982) involved a contractor who sought to recover $99,076 in operational costs incurred on a construction contract during a two-month period in 2020. The APTIM decision expressly addresses the Sovereign Acts defense, which ultimately denied the contractor’s claim for additional compensation. APTIM Federal Services, LLC (ASBCA No.